Electricity In Nigeria: TCN Explains Why There’s Nationwide Blackout


As the blame-game for the low electricity generation continues, the Transmission Company of Nigeria (TCN)  has accused the generation companies (GENCOs) for the nationwide blackout.

“The media has been awash with reports that TCN has reduced the load allocation to distribution companies. That information is incorrect. The correct position is that TCN can only transmit the quantum of power generated by GenCos through the national grid to distribution load centres nationwide.

“For clarity, TCN does not generate electricity and therefore can only transport cumulative generation from all the generation companies nationwide to distribution load centres. The distribution companies are responsible for end-users consumption. TCN allocates power to distribution companies based on approved percentage (formula approved by Nigeria Electricity Regulatory Commission (NERC), of the total generation available per hour or on day-ahead nomination” TCN said in a statement.

The statement also noted that presently,  the cumulative generation nationwide is low and generation companies have attributed this to several factors including poor gas supply, fault in generating units of generating companies, scheduled and unscheduled maintenance, all of which have caused most power generating companies to limit their generation, and sometimes not  generate at all.

Also Read:  Power: Why Delta, Edo, others will experience darkness for four weeks - TCN

A summary of the power generating profiles,  in the last two months, for instance,TCN, explained, clearly shows that 14  gas powered generating stations were either not generating at all or had limited generation at various times within the period, further depleting the quantum of power generation available for transmission into the grid on a daily basis.

“Power generating stations in this category include; Omotosho units 5 and 6, Olorunsogo units 3, 4  and  6, Omoku units 3  and  6, Omotosho National Independent Power Plant  (NIPP) units 3 and  4, Delta units 15, 17, and 18, Afam VI units 11 and 12, Olorunsogo NIPP unit 3, Ihovbor NIPP unit 2, Sapele Steam unit 3, Sapele NIPP unit 1, Odukpani NIPP units 1 and  3, and Okpai units 11, 12 & 18.

“Also, within the same period, Jebba Hydro and Shiroro Power Generating Stations were either out or had limited generation, causing additional loss of 232MW from the grid, while other power generating plants such as  Omotosho units 3 and 4, Olorunsogo units 1, Delta units 10 and 20, Afam VI  unit 13, Ihovbor NIPP units 4, Geregu NIPP units 22 and 23 and Odukpani NIPP units 2, 4  and  5, have also been out either on fault or for scheduled maintenance, causing a further loss of about 3,180MW from the grid.

Also Read:  NERC Approves Increment In Electricity Tariff

“A combination of the above scenarios have persisted and the total effect on the grid is persistent low generation, which TCN operators have had to strive to dispatch in a way that will not jeopardise the stability of the grid.

More recently, from the 1st to 4th of March, 2022, there was generation shortfall due to water management in Shiroro and Jebba hydro with the loss of 307MW and 125MW respectively from both stations. Within the same period, there were fault and technical problems in Egbin, causing 514MW shortfall and in Geregu causing 230MW shortfall, while reported fault at Alaoji NIPP reduced generation from the substation by 263MW.

“Gas constraint alone in Olorunsogo gas generating plant reduced generation from the station by 104MW, in the same vein,  Omotosho gas lost 102MW and Sapele NIPP lost 263MW. In Omotosho NIPP, there was generation shortfall of 233MW and in Omoku a shortfall of 112MW. Two units in Okpai have limited generation due to technical problems causing a 204MW drop in generation and in Afam VI 511MW drop in generation.

Also Read:  VIDEO: Niger Delta Militants Warn FG, Oppose Choice Of Tompolo On Pipeline Surveillance Contract

“Gas constraint and fault in Olorunsogo NIPP reduced generation by 240MW, Geregu NIPP by 435MW, and Ihovbor by 142MW.  Also, due to gas pipeline pigging, Odukpani NIPP was SHUT DOWN which caused a reduction of generation by 575MW” the company, noted.

Sun


LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.